Changing Places facility update: internal fit-out and external works progress

Published on 4 June 2025

 


The Changing Places facility at Main Beach, Ocean Grove, is progressing well, with the internal fit-out now nearing completion. A key feature is the newly installed hoist and track system, which will assist carers in safely transferring people with high needs.

Externally, the site has been prepared for the first stage of concreting works, taking place this week within the current worksite fence boundary. Landscaping works will also continue throughout the week.

Following this, the second stage of concreting will include a new pathway connection and replacement of a section of the existing pathway. These works have been carefully staged to minimise disruption for pedestrians and cyclists.

When the second stage begins, a section of the pathway will be temporarily closed and detours will be put in place. Further details and timing will be shared closer to the commencement of those works. 

Related Articles

2025-26 Annual Report released

Our 2025-26 Annual Report is now available online.

Read Article

New Barwon Heads cabins officially launched

An update on construction activities at Barwon Heads Caravan Park

Read Article

Notice to Mariners No. 415 – 2026

Barwon Heads – Barwon River Bar Depths Compromised

Read Article

Update on Surf Bridge North and South beach access tracks

We continue to closely monitor conditions at the Surf Bridge North and Surf Bridge Southbeach access tracks at RAAFs Beach.

Read Article