Key Project Dates

December 2024 - May 2025

Stage 1: Community survey open 100%

1 - 31 March 2025

Stage 2: Community and Stakeholder Design workshops 100%

August 2025 - February 2026

Stage 3: Developing a draft Master Plan 100%

1 June 2026

Stage 4: Draft Master Plan released for feedback 100%

25-27 June 2026

Stage 5: Community Information Sessions 100%

July-September 2026

Stage 6: Incorporate feedback and develop final Master Plan 100%

October 2026

Final Master Plan released 100%

 

Foreshore Master Plan

Published on 12 December 2024

About the Foreshore Master Plan

The Barwon Coast Foreshore Master Plan is a 15-year guide for the protection, access, improvement and long-term care of approximately 22 kilometres of coastal Crown land, from Breamlea to Collendina, that is managed by Barwon Coast.

Prepared by Barwon Coast in partnership with Hatch Design, the Master Plan establishes a forward-looking, landscape-first framework for all public coastal land under its care, including Breamlea, Bancoora Beach, Black Rock, Thirteenth Beach, Barwon Bluff, Barwon Heads Foreshore, Bukareeyoo, Ocean Grove Main Beach, and Collendina.

Our coast. Our shared direction.

22 kilometres. 15 years. One shared direction for our coast.

More than 1,200 voices have helped shape Barwon Coast’s Foreshore Master Plan – a 15-year roadmap for the future management of the coastline in our care.

Throughout the development of the Plan, community members, Wadawurrung Traditional Owners, our Community Reference Group, stakeholders, community organisations and visitors shared their knowledge, experiences and aspirations for the coast.

That knowledge has been fundamental to understanding what people value, what needs attention and what should be protected for the future.

The final Plan seeks to balance caring for Country, protecting and restoring the coastal environment, providing safe and sustainable access, and supporting the many ways people experience and enjoy our coast.

Final Foreshore Master Plan

Closing the Loop Engagement Report

You shared your knowledge. You helped shape the Plan. Now we move forward together.

What happens next

The Foreshore Master Plan sets the direction – now we begin putting it into action.

Implementation will happen progressively over the next 15 years, with projects moving forward as planning, design, approvals, partnerships and funding allow.

Some of the first priorities include:

  • Progressing detailed designs for the Lahey Square and Flinders Parade precinct
  • Continuing design work for improved ramped access at Ocean Grove Main Beach, near The Dunes
  • Design of the rear Barwon Heads Caravan Park overflow car park to help manage seasonal demand and support appropriate access for Barwon Heads Football Netball Club patrons.
  • Continuing planning and design for renewed facilities and sewer connections at Bukareeyoo
  • Working with project partners on new public toilet facilities at Bancoora Surf Life Saving Club
  • Progressing entrance and accessibility improvements at the Barwon Coast Discovery Centre
  • Continuing to implement recommendations from Barwon Coast’s accessibility audit.

Planning will also continue for projects and priorities across the broader 22 kilometres of coastline, including Breamlea, Bancoora, Black Rock and Thirteenth Beach.

The first five years of the Master Plan will help inform the renewal of Barwon Coast’s Coastal and Marine Management Plan during 2027.

Not every Master Plan action will commence immediately. Projects will be progressively investigated, designed and delivered based on need, feasibility, coastal and environmental conditions, approvals, partnerships and available funding.

Where projects require further consultation, there will be opportunities for people to help shape the detail as work progresses. The Plan gives us the shared direction. These projects are some of the first steps towards delivering it.

Foreshore Master Plan Development timeline

The Foreshore Master Plan project started in 2024 and was completed in October 2026.

How we grounded the draft Master Plan in evidence and community insight

Community insight

Community consultation for the Foreshore Master Plan was undertaken in two key stages, designed to progressively inform the development, testing and refinement of the Plan.

Stage 1 – Understanding values and aspirations (November 2024 – July 2025) focused on understanding what the community values about the Foreshore, how people use and experience different places, key issues and opportunities, and aspirations for the future. This feedback, together with input from the Community Reference Group, Wadawurrung Traditional Owners, stakeholders and agencies, informed the development of the Master Plan’s overarching vision, principles and early concepts.

– Stage 2 – Feedback on the draft Foreshore Master Plan (1 June – 6 July 2026) sought community and stakeholder feedback on the draft Plan, including the proposed directions, precinct concept plans and actions. Feedback was used to test whether the draft appropriately reflected community values and priorities, identify areas requiring further consideration and inform changes incorporated into the final Foreshore Master Plan.

Technical Reports

Four key technical documents are guiding this work:

  • Accessibility Audit: Identifies physical and social barriers across coastal sites and highlights opportunities to make our coast more inclusive. See the ‘Creating Connection: Places & Spaces Access Audit’ (released 6 December 2025).
  • Bancoora Coastal Adaptation Plan: Developed with Wadawurrung Traditional Owners, this plan explores how we respond to climate-driven coastal hazards like erosion and inundation at Bancoora Beach and foreshore. The final Adaptation Plan was released to the public on 6 August 2026.
  • Coastal Hazards Exposure Report: Uses the best available science and local knowledge to refine our understanding of coastal hazard risks—informing safer, more resilient future planning. This Technical Report was released to the public on 18 February 2026.
  • Barwon Coast Biodiversity Strategy: Sets out goals and actions to protect and enhance biodiversity across Barwon Coast-managed land, ensuring long-term ecological health. The final strategy was released on 14 May 2026.

These strategies, reports and audits are essential tools in shaping future actions. They provide evidence-based direction that supports the values and aspirations expressed by the community.

Frequently asked questions

About the Foreshore Master Plan

Who is Barwon Coast?

Barwon Coast Committee of Management Inc (Barwon Coast) is delegated by the Victorian Minister for Environment to manage 22km of the coast along Victoria’s Bellarine Peninsula. This includes the beaches and foreshores of Collendina, Ocean Grove, Barwon Heads, 13th Beach, Black Rock and Breamlea. In partnership with Traditional Owners, Barwon Coast’s charter is to protect and enhance the natural environment and provide opportunities for residents and visitors to enjoy these areas.

Barwon Coast operates three caravan parks and one campground in the foreshore reserve, as well as managing various community and commercial leases and licences. All revenue raised is reinvested to care for the natural environment and to provide facilities and infrastructure along the coast for use and enjoyment by all.

What is a ‘Master Plan’?

‘Master Plan’ can mean different things to everyone. To determine what a Master Plan would look like for the Barwon Coast Foreshore, we worked with Traditional Owners, community members, the Community Reference Group and stakeholders to develop a shared vision for the Foreshore.

The Barwon Coast Foreshore Master Plan is a 15-year guide for the protection, access, improvement and long-term care of approximately 22 kilometres of coastal Crown land managed by Barwon Coast, from Breamlea to Collendina.

Why is a Master Plan needed?

The final Foreshore Master Plan sets out Barwon Coasts direction and a significant amount of its program of work for the next 15 years. It ensures that Barwon Coast is responding to pressures like population growth, ageing infrastructure and coastal hazards (erosion and sea level rise), as well as guide investment to ensure we continue find the right balance between meeting the needs of our communities while protecting and enhancing our natural environment.

In addition, the Barwon Coast Coastal and Marine Management Plan 2020-2025 (CMMP) is due for renewal in 2027. The outcomes of this project will inform development of a new CMMP.

Who developed the draft Master Plan?

Barwon Coast worked with Hatch Design to develop the Master Plan. We also worked closely with our communities, a Community Reference Group and stakeholder organisations, including Wadawurrung Traditional Owners Aboriginal Corporation, Department of Energy, Environment, Climate Action (DEECA), Department of Transport and Planning, City of Greater Geelong, Barwon Water, Corangamite Catchment Management Authority and Parks Victoria.

Did Barwon Coast complete a master plan a couple of years ago?

Yes. The Camping and Caravan Parks Master Plan, which sets out Barwon Coasts accommodation needs for the next 10 years, was approved in 2023. The Foreshore Master Plan does not review the accommodation needs reviewed camping and caravan park areas in relation to public access and facilities through the Foreshore reserves. However, due to key feedback heard during our community consultation, Bukareeyoo recreational opportunities have been considered in more detail which has impacts on some camp sites.

How does the Master Plan work?

The Master Plan is a layered document and is designed to be read in layers. It starts with the full 22 km Foreshore and gradually zooms in to precincts, key places, priority actions, design ideas and delivery steps.

This Master Plan works at three scales; we start big, then zoom in.

  • The Foreshore-wide map shows the full 22 km coast. Use it to understand how the network connects as a whole. The pink line is the primary coastal path. Blue and brown lines are supporting connections.
  • Precinct plans: Find your precinct and read the local detail. Each precinct plan shows trails, nodes, biodiversity zones and key actions for that area.
  • Concept plans zoom into priority locations and show specific layout, access and infrastructure changes. Actions are numbered and colour-coded by priority.
How does the draft plan consider climate change?

The Coastal Hazard Exposure Report (CHER) and Bancoora Coastal Adaptation Plan (CAP) are foundational inputs to the draft Master Plan.

As climate change intensifies, so do the impacts of sea level rise, erosion, storm surge and inundation. These are collectively named coastal hazards, and they pose a growing risk to infrastructure, access, environmental values and the long-term function of the Foreshore. These dynamic risks are central to every planning decision. The CHER defines the physical and temporal parameters of the coastline, identifying where hazards occur today and how they are projected to evolve. It provides the primary evidence base for risk-informed planning and basis for a mitigation hierarchy, found in the draft Plan, which guides how the Master Plan responds to coastal hazards.

The mitigation hierarchy follows a clear logical sequence:

1. Avoid risk where possible.

2. Adapt where change is needed.

3. Transition over time where places can no longer support the same use.

This helps ensure access, land use and infrastructure decisions work with coastal processes, reduce future risk, and support long-term resilience.

Will the Plan increase development along the coast?

The Plan seeks to carefully manage and minimise impacts on the foreshore. Improvements are intended to be balanced with environmental protection and landscape character.

How are sensitive coastal areas being protected?

The Plan uses ecological sensitivity, coastal hazard exposure, the Biodiversity Strategy 2025-35, the Mature Tree strategy and cultural values to guide where access, infrastructure and activities are appropriate or limited.

Community consultation and engagement
How was the community involved in the development of the draft Master Plan?

Community and stakeholder input has directly informed the direction of the final Plan. The Community Reference Group (CRG), established through an open Expression of Interest in late 2024, brought together approximately 20 members representing local residents, landowners, sporting clubs, and conservation and community organisations. The CRG played an ongoing role in testing ideas and shaping outcomes, and was the group’s work concluded in October 2026.

Wadawurrung Traditional Owners contributed through workshops and direct collaboration, strengthening understanding of Country as an interconnected system of land, water, culture and story. This knowledge has informed the Shared Values, priorities and key frameworks that guide how the Foreshore is planned, experienced and cared for.

How was the community consulted during the development of the Foreshore Master Plan?

Community consultation for the Foreshore Master Plan was undertaken in two key stages, designed to progressively inform the development, testing and refinement of the Plan.

Stage 1 – Understanding values and aspirations (November 2024 – July 2025) focused on understanding what the community values about the Foreshore, how people use and experience different places, key issues and opportunities, and aspirations for the future. This feedback, together with input from the Community Reference Group, Wadawurrung Traditional Owners, stakeholders and agencies, informed the development of the Master Plan’s overarching vision, principles and early concepts.

– Stage 2 – Feedback on the draft Foreshore Master Plan (1 June – 6 July 2026) sought community and stakeholder feedback on the draft Plan, including the proposed directions, precinct concept plans and actions. Feedback was used to test whether the draft appropriately reflected community values and priorities, identify areas requiring further consideration and inform changes incorporated into the final Foreshore Master Plan.

Governance
Which state government policies and guidelines provide direction for the Master Plan?

The Marine and Coastal Act 2018 and Marine and Coastal Policy 2020 were the key statutory and policy frameworks underpinning the Master Plan. They guide decision-making and established the planning concepts, including the definitions of activity nodes and recreation nodes, that direct use, organise infrastructure and minimise impacts on the coastal environment (DELWP, 2020).

What are activity nodes and recreation nodes?
  • Activity nodes provide for community recreation facilities and tourism activities. They sit within settlements, adjacent to activity centres in planning schemes, and include (but are not limited to) major beach arrival areas, cycling infrastructure, beach access points and boardwalks.
  • Recreation nodes sit on marine and coastal Crown land outside activity nodes. They provide access and infrastructure for recreation and water-related activities. Use and development that supports access or the functioning of coastal-dependent activities, may be located in recreation nodes. Typical assets include car parks, lighting, CCTV, wayfinding signage, picnic and seating facilities, and services such as community clubs.
What policies, plans and technical reports have been considered as part of the Master Plan?

The Master Plan draws on a structured review of policy, legislation and supporting documents, establishing the statutory framework, strategic direction and evidence base for all planning decisions.

• Marine and Coastal Act 2018
• Marine and Coastal Policy 2020
• Planning and Environment Act 1987 (Vic)
• Victorian Planning Provisions
• Bellarine Peninsula Statement of Planning Policy – Distinctive Areas (2023)
• Surf Coast Statement of Planning Policy – Distinctive Areas (2021)
• Siting and Design Guidelines for Structures on the Victorian Coast (2020)
• Aboriginal Heritage Act 2006

Statutory and Management Plans
• Barwon Coast Coastal and Marine Management Plan (CMMP)
• Barwon Bluff Marine Sanctuary Management Plan (2007)
• South East Bellarine Coastal and Marine Management Plan

Strategic and Regional Frameworks
• Wadawurrung Country Plan 2020–2030
• Corangamite Regional Catchment Strategy
• Rivers of the Barwon (Barre Warre Yulluk) Action Plan
• Kitjarra-dja-bul Bullarto langi-ut Masterplan (2023)
• Sustainable Destination Master Plan – Geelong & The Bellarine (2023–2033)
• Greater Geelong Cycle Strategy
• City of Greater Geelong Shared Trails Master Plan
• Conservation Action Plan: Basalt Plains and Bellarine Peninsula, Parks Victoria
• Wadawurrung Signage Guidelines

Coastal and Environmental Technical Reports
• Barwon Coast Foreshore Coastal Hazard Exposure Report
• Coastal Hazards and Coastal Adaptation Assessments
• Barwon Coast Biodiversity Strategy (2025-35)
• Creating Connection: Places & Spaces Access Audit (2025)
• Wadawurrung Wiyn Cultural Fire Strategy Healing Country with Fire 2024-2034

Site-Specific and Precinct Plans
• Barwon Coast Caravan and Camping Master Plan (2023)

Does the Plan override planning or environmental laws?

No. Any future works will still require relevant approvals, environmental assessments and compliance with state and local legislation and policy.

Next steps and implementation
What happens next?

The Foreshore Master Plan sets the direction – now we begin putting it into action.

Implementation will happen progressively over the next 15 years, with projects moving forward as planning, design, approvals, partnerships and funding allow.

Some of the first priorities include:

  • Progressing detailed designs for the Lahey Square and Flinders Parade precinct
  • Continuing design work for improved ramped access at Ocean Grove Main Beach, near The Dunes
  • Design of the rear Barwon Heads Caravan Park overflow car park to help manage seasonal demand and support appropriate access for Barwon Heads Football Netball Club patrons.
  • Continuing planning and design for renewed facilities and sewer connections at Bukareeyoo
  • Working with project partners on new public toilet facilities at Bancoora Surf Life Saving Club
  • Progressing entrance and accessibility improvements at the Barwon Coast Discovery Centre
  • Continuing to implement recommendations from Barwon Coast’s accessibility audit.

Planning will also continue for projects and priorities across the broader 22 kilometres of coastline, including Breamlea, Bancoora, Black Rock and Thirteenth Beach.

The first five years of the Master Plan will help inform the renewal of Barwon Coast’s Coastal and Marine Management Plan during 2027.

How will the Master Plan be implemented?

The final Master Plan included timelines for actions (e.g. 0-5, 5-10 and 10-15 years), and Barwon Coast will develop an implementation plan including costs estimates and potential funding sources.  A quantity surveyor has been engaged to provide cost estimates.  The implementation plan will guide Barwon Coast’s operational budgets and yearly works schedule. Actions will be implemented by Barwon Coast staff, contractors and consultants (depending on the required skills, timing and expertise).

Who will pay for implementing the Master Plan actions?

The Foreshore Master Plan is a long-term guide to help shape decision-making and future investment across the coast over the next 15 years. While the Plan identifies a broad range of actions and opportunities, it is unlikely that all actions will be delivered within this timeframe.

Implementation will occur progressively and be subject to available funding, approvals, environmental assessments and changing community priorities. Funding may come from a range of sources, including Barwon Coast investment, government partnerships (Federal, State and Local), grant opportunities, private sector investment and philanthropic contributions.

Will all these actions definitely happen?

The Master Plan does not approve every action for construction, guarantee funding or remove the need for further design, approvals, cultural and community engagement, environmental assessment or feasibility testing; Some will require further investigation, approvals or detailed design before implementation.

The Master Plan provides a clear decision-making framework to help Barwon Coast, Wadawurrung Traditional Owners, government agencies, partners and the community make better decisions over time.

Actions will be reviewed and adjusted over time in response to:

  • Coastal erosion and sea level rise.
  • Changes in habitat condition.
  • Visitor pressure and use patterns.
  • Cultural guidance and priorities.
  • Approvals and funding pathways.